Cost Economics of Greenhouse
   
     


 
High cost green house may be a multispan structure. The cost estimates may vary considerably due to crop, cladding material and environmental control system. The additional cost involved per sq. m. is stated below.

Sr.No Specifications Cost Rs/m2
1 If double layer polyethylene used 100
2 Co2 generation & distribution 150
3 Evaporative cooling 200
4 Heating system 100
5 Humidification system 100
6 Lighting 200
7 Night curtain / Shading system 150
8 Drip system 20
9 Nutrient application system 100
10 Porous flooring 100
11 Benches 150
12 Structural cost 300
13 Miscellaneous 180
Average cost of High Cost
Greenhouse per square metre Rs. 2000.00




Detailed estimate of material requirement for simple Pipe framed low cost green house (4x25m)

Sr.No. Item of work / Detail of material Requirement (Qty)
1 G.I. Pipe of 25 mm. f for foundation 50 x 1.20 =60m
2 G.I. Pipe of 15 mm. f for arches and top M.S Flates 19x8m 25 x 6 = 150m 25 x 1 = 25m
3 For sides for holding mesh and UV film and front & backside &for purlins 120.00m run
4 M.S. ‘L’ angle19x19x3m for front and end frames and door 28m run
5 Plastic beading 25 mm width 150 m
6 UV stabilised film (200 micron) 175 m2
7 Mesh 40-60 size all round (1.15m width) 65 m
8 Door frame and fitting L.S
9 Hardware like Bolts and nuts, welding rods, Aluminium oxide, Painting etc. L.S
10 Earth work and concreting of foundation with 1: 3: 6 L.S
11 Labour cost L.S



Cost Economics of Simple, pipe framed green house (100 m2)

Sr. No Item of work Qnty. Rate / unit (Rs) Total amount (Rs)
1 G.I. Pipe 25 mm dia.’B Class 60.0m 65.00/= 3900
2 G.I. Pipe 15 mm dia. ’B Class 175.0m 25.00/= 4375
3 M.S.Flat 19x3mm Size 80.0kg 16.50/kg 1320
4 M.S.L angle 19x19x3mm Size 20.0kg 17.50/kg 350
5 UV stabilised film 175.0m2 20.00/= 3500
6 Plastic beading 150.0m 4.00/= 600
7 Mesh 40-60 size all round 65.0m2 22.00/= 1430
8 Door frame and fitting L.S 425
9 Labour cost L.S 650
10 Bolts, nuts and welding rods L.S 400
11 Earth work and concreting of foundation L.S 550
Total  17,500.00

 
 
 